The Chervona Shapochka kindergarten in Mykhailivka-Rubezhivka, part of the Irpin community, is being completed together with a radiation shelter. It will cover more than 1,000 square metres and hold 200 people.
This was reported by Irpin’s first deputy mayor Oleksandr Pashchynskyi.
In April the community received a state grant of 42.9 million hryvnias for the shelter. Another 8.5 million was added from the local budget as co-financing.
The shelter will have rest areas with beds and play zones. Accessibility has also been planned so that everyone can use it comfortably.
This year the community also allocated money to complete the kindergarten’s second building. However, after the project was revised, the amount of funding required went up.
Work is continuing, but the project faces technical, organisational and financial difficulties. These were discussed during a site visit with Kyiv Regional Military Administration head Tymur Tkachenko, with the aim of using the state and local funds by the end of the year.
Why a 35 million hryvnia purchase was cancelled
Irpin’s executive committee chose a contractor for the second building with the shelter back in September 2025. The 87 million hryvnia contract went to ZZh Kyiv LLC, the only bidder.
On 2 October the committee launched a negotiated procedure for additional work with the same contractor, worth almost 34.9 million hryvnias excluding VAT. But on 16 November it was cancelled because the identified breaches of public procurement law could not be remedied.
As a reminder, roof replacement has begun at the Lisova Pisnia kindergarten in Irpin.