Bucha City Council has reached an agreement with Avtomahistral-Zakhid LLC, the general contractor rebuilding Enerhetykiv Street. In October the city was raising the question of ending the contract, but now work on the central street of Bucha has noticeably picked up.
This was reported by Bucha Mayor Anatolii Fedoruk.
The mayor says he receives many complaints from residents and understands their frustration with the delays. In his view the pace could be even faster, so he is keeping the situation under his personal control.
By the end of the year the contractor promises to prepare the base for paving slabs along the entire street. Meanwhile, the neighbouring buildings are being reconnected to the upgraded water mains.
What has already been done
The biggest stage is already behind them: new water mains, sewers, storm drains and power lines have been laid under the street. Since mid-November paving has been laid on the section from Bohdana Khmelnytskoho Boulevard to Polova Street.
What the street should become
Enerhetykiv Street is the first phase of a barrier-free route under the national Movement Without Barriers project, which includes 15 communities. The whole Bucha route is 3.6 km long: besides Enerhetykiv, it covers Polova Street, Bohdana Khmelnytskoho Boulevard and Nove Shose.
The 0.93 km street is to get a pedestrian zone with restricted traffic, tactile paving, safety islands, a cycle lane and parking for people with disabilities. All 32 businesses and institutions on this stretch have agreed to adapt their premises.
A tender won by 98 kopecks
The tender was announced in October 2025 with an expected value of 212.2 million hryvnias from the local budget. At the auction Avtomahistral-Zakhid cut its price to 169.3 million and beat the runner-up, NIDKOM LLC, by just 98 kopecks.
The contract was signed on 20 November 2025 and runs until 31 December 2026. At the end of December a second contract worth 49.2 million was signed with the same contractor for work under a revised design. The two contracts total 218.4 million hryvnias.
Why the repair dragged on
In summer 2026 the general contractor suspended work. The company blamed the delays on its workers losing their draft deferrals, staff shortages and disrupted supplies of materials after russian strikes on factories.
In September the mayor explained at a council session why the city was in no hurry to replace the contractor: a new tender would take at least 45 working days, and the price could fall to an abnormally low level.
In early October the council formally proposed that the contractor end the contracts because of the delays. In the end, however, the two sides reached an agreement.
As a reminder, Bucha has become one of four pilot communities for the national barrier-free plan.
Nota bene
Bucha FM is an independent news site and station for the Bucha district. We cover what matters to the community, and we work for you — and because of you. Joining the people who make this possible is simple: support us with any amount.